• About Us
  • Capabilities
  • Projects
  • Our Commitment
  • Careers
  • Contact Us
Header3.jpg
General Construction Company
  • About Us
    • Culture
    • History
    • Working with us
  • Capabilities
    • Marine
    • Industrial
    • Heavy Civil
    • Design Build
    • Equipment Fleet
  • Projects
    • Marine
    • Industrial
    • Heavy Civil
  • Our Commitment
    • Safety
    • Quality
  • Careers
  • Contact Us
Hide Search Field
Show Search Field

Outfalls and Intakes

Home    »    Projects    »    Marine    »    Outfalls and Intakes

Projects

  • Marine
    • Wharves and Piers
    • Outfalls and Intakes
      • Kingston Outfall
      • Lake Youngs Intake
      • Midway Sewer District Submarine Outfall
      • Post Point Alternative Outfall
      • South Bay Ocean Outfall
    • Jetties and Breakwaters
    • Dredging
    • Ferry Terminals
    • Marinas
    • Heavy Lifting
  • Industrial
  • Heavy Civil
Kingston Outfall

Kingston Outfall

Kingston, Wash.

The first 1,200 ft of pipe was installed on the beach with conventional land equipment from behind the Kingston Marina out to the zero tide mark. The next 500 ft was laid and backfilled one joint at a time during high tides from a derrick barge offshore. The next 2,200 ft was installed and backfilled in a pre-excavated 6-9 ft ditch in 96 ft sections. The ditch was backfilled first with gravel and quarry spalls, then native material previously removed. The final 1,400 ft was laid directly on the bottom out to a set of diffusers at -170 MLLW. All underwater connections were made with divers. At the outer end of the outfall a four-diver crew was required, with each diver only having 14 minutes of bottom time due to the depth.

Read More
Lake Youngs Intake

Lake Youngs Intake

Seattle, Wash.

This project required construction of a steel intake pier 450 ft into an active drinking water reservoir. Our work included 500-tons of fabricated steel supported by 22 piles in four piers. The 175 ton, 50 x 100 ft pump platform was assembled in place before lowering 20 ft and driving piles. In completed form it has steel walls and floor, slide gates, a jib crane and 8 pumps manifold to twin 6 ft pipes back to the beach. The work required a trestle, sheet cell, sectional barges with a 165-ton crane and extensive silt curtains.

Read More
Midway Sewer District Submarine Outfall

Midway Sewer District Submarine Outfall

Kent, Wash.

he initial 285 ft of pipe was installed through a jacked and bored casing installed by a subcontractor. This runs from the Des Moines Beach Park, under a hill, and out the upper portion of the beach. The next 600 ft were installed at low tides with an excavator in a sheet pile trench. All work was performed on non-floatable mats to protect the beach. The next 400 ft of pipe going offshore was installed by divers and a derrick barge in an excavated trench with sheet pile to protect the eel grass. Past the sheet pile, the pipe continues in an excavated trench for 200 ft then daylights and was set on the bottom out to the station 21+00. Precast anchors were set over the unburied section of pipe.

Read More
Post Point Alternative Outfall

Post Point Alternative Outfall

Bellingham, Wash.

The project began with the relocation of approximately 1,000 sq ft of eelgrass. Then a 250ft long by 50 ft wide trench was dug. Serving as a foundation for the diffuser, three, 4 ft by 12 ft articulated concrete ballast mats were placed at in 55 ft of water in Puget Sound. The 620 ft. long, 54 inch HDPE outfall pipe was sealed at each end and pulled from the beach into the water. While it was floating, 23 concrete weights were attached. Each weight was over 15,000 pounds. After attaching the onshore end to its tie-in point, we used controlled submergence to sink the pipe into the trench and onto the mats. Finally the trench was backfilled and the beach was restored to its previous appearance.

Read More
South Bay Ocean Outfall

South Bay Ocean Outfall

San Diego, Calif.

General Constructions work started almost 2 miles offshore where an outfall tunnel is connected to the seabed by a 9 ft. diameter riser structure. The 10 ft. diameter seabed outfall trunk line originates at the riser and proceeds west for 4,500 ft., to a 320-ton wye structure. From the wye structure, two diffuser lines extend 2,000 ft. to the north and south along the seabed. This project required dredging 210,000 cubic yards of excavation, and placement of 350,000 tons of rock to bed, ballast and armor the 1.6 miles of outfall pipe. All work was performed 2 to 4 miles offshore, and at an average depth of 100 ft.

Read More
Careers

Apply Now!

GCC is a subsidiary of Kiewit Corporation. This link will direct you to Kiewitjobs.com where you’ll find a comprehensive list of all Kiewit and subsidiary staff opportunities. If you would like to view GCC jobs only, use the search tool to narrow results.

 
Featured Projects
Benicia-Martinez Bridge
Benicia-Martinez Bridge
Oakland, Calif.
Read More
Oakland Bay Bridge Skyway
Oakland Bay Bridge Skyway
San Francisco, Calif.
Read More
Contact GCC

Corporate Office:

33455 6th Avenue South

Federal Way, WA 98003

General Info : info@GCC.com

Apply Now!

 

GCC is a subsidiary of Kiewit Corporation. This link will direct you to Kiewitjobs.com where you’ll find a comprehensive list of all Kiewit and subsidiary staff opportunities. If you would like to view GCC jobs only, use the search tool to narrow results.

 

Featured Projects

Benicia-Martinez Bridge
Benicia-Martinez Bridge
Oakland, Calif.
Read More
Oakland Bay Bridge Skyway
Oakland Bay Bridge Skyway
San Francisco, Calif.
Read More

Contact GCC

Corporate Office :

 33455 6th Avenue South
Federal Way, WA 98003
Tel: (253) 943-4200
Fax: (253) 943-4021 

 

General Info : 

info@GCC.com

 
© 2021 General Construction Company. All Rights Reserved.
  • Privacy Policy
  • Terms & Conditions
  • Sitemap
  • Search
Top
Menu